Location:
Sudan-Khartoum City
Activity:
Sewerage Systems and Environment
Client:
Khartoum Sanitary state corporation (KSSC)
start date:
Completion Date:
Project Description:
Type of Service : Design , implementation Supervision and Project Management
Purpose of the Project: Supply & Installation of Pressure pipes from
Existing Pumping Station in Algoaz-Soba Installation of Pressure Main of 700 mm of G.R.P pipes to transmission untreated waste water from Algoaz P.S.NO.21 to Soba P.S.NO.30 at treatment lagoon, about 10 km length
Length of pipe line: 10 km
pipe Diameter: 700 mm
Type of transmission: Pressurize
Status of the
project: under construction