Location:
Sohanak, Tehran
Activity:
Water Supply
Client:
Tehran province water & wastewater Co.
start date:
Completion Date:
Project Description:
Services: First and Second stages of studies,Observation & supervision
Objective: Water treatment to provide part of drinking water needs in Tehran
Capacity: 5.7 m³/ day
Water Supply : Lar and Latian Dams
Transmission Method :Pipe and Ghochal Tunnel
Treatment method: initial chlorination, coagulation, flocculation, clarification by pulsator, V Akazor filtration ,sedimentation, secondary chlorination
The total area of the treatment plant : 12 hectares
Start date of exploitation : 2004 year
Water supply : Lar and Latian Dams
Transmission Method :Pipe and Ghochal Tunnel
Treatment method: Initial chlorination, coagulation,flocculation, clarifi Akazor filtration sedimentation, secondary chlorination
The total area of the treatment plant : 12 hectares
Start date of exploitation : 2004 year