Location:
West coast of ChahNimeh No.3
Activity:
Water Supply
Client:
Sistan Baluchistan Regional Water Company
start date:
Completion Date:
Project Description:
Services:Design and supervision on execution
Population coverage:370,000
Main components:Water intake, transmission line and treatment plant
1. Intake
installation
Intake method: Concrete towe
Intake capacity:5 m³/ sec
Pumps type:Submersible
2. Treatment plant
Treatment capacity: 2050
lit/sec
Location: West coast of ChahNimeh No.3
Treatment method:Coagulation, flocculation, pulsator
clarification, filtration
Disinfection:Ozone inject, final chlorination
Coagulating agent:Fluoric chlorine, lime polyelec trolyte
(PH adjust)
3. Transmission
line
Pipe diameter:1200 – 1600 mm
Pipe material:Ductile iron, UPVC
Transmission length:140 km
Pump stations:7 units
4. Water
reservoirs
Reservoirs volume:59000 m³
Reservoirs quantity:11
Status:Under operation