Ashkhaneh Wastewater Treatment Plant

Ashkhaneh Wastewater Treatment Plant

Location: North Khorasan Province Ashkhaneh

Activity: Sewerage Systems and Environment

Client: Khorasan Shomali Water & Wastewate Company

start date: 1390/09/01

Completion Date:

Project Description:

Project period : beginning of 2011 , end of 2036

Population : First 21700  people end of 50000 people

Total Length of the collecting network: 75 km

Pipes used : double -wall Corrugated polyethylene Specifications of the development plan for wastewater treatment plant 

Treatment process: Active aerated mass sludge with the ability to remove phosphorous and nitrate with a capacity of 8309 cubic meters per day and with a covered population of 50666 people

Project Status: Waste Water Treatment plant and pumping station and 16 km of sewage collection network in operation