Location:
Sungun copper mines, 120 kilometers to North – West of Tabriz
Activity:
Dams and Water Resources
Client:
Iranian Mines and Mineral Industries development and Reconstruction organization-National Iranian Copper Industries Company-Integrated water plan
start date:
1388/01/01
Completion Date:
Project Description:
Services: Design & construction supervision
Objectives: Development & Rehabilitation of Raw
water supply and tailings disposal of Sungun copper
mine
Upgrading
Tailing Dam & Waste Disposal System:
1. Actual height of tailing dam at the end of mine’s
operation
period (30 years) 178 m
2. Two Tailings pump stations for waste transmission with
50%
tail
density and 1375 m3/hr discharge and pumping head of
5985 kpa
3. Two Tailings pipe lines; each of them has 10 km length
with
450 mm & 500mm diameters
Return
water transfer system
1. Two pontoon pump stations, one station with 2600 m3/hr
discharge capacity and pumping head of 160 m and the other
one with
2000 m3/hr discharge capacity and pumping head
of 50 m
2. Steel return water pipelines, total 11km length, with 900 and
400 mm diameters
Raw
water supply system from Ahar Dam
1.Two pump stations with discharge capacity of 320 m3/hr
and
420 m3/hr and pumping head of 1260 m at the
Ahar Dam
2. Two steel pipelines with length of 36 Km and 300 mm &
400mm diameters from Ahar Dam to Sungun mine
Raw
water supply system from Hajlarchai Dam
1. Two pump stations with discharge capacity of 1266m3/hr
and
total pumping head of 811 m at
2. Steel pipeline with length of 47 Km and 65mm diameter
from
Hajilarchai Dam to Sungun mine
Studies
started: 2009
Status:1st
phase of project is under operation and a part of development plan (2nd phase)
is under construction and the other part is under operation